IH 10 Frontage Road Rehabilitation Project - Washington Avenue to Taylor Street

Scope of Work: Rehabilitate and reconstruct existing frontage roads and construct new frontage road bridges over White Oak Bayou west of Yale Street. The scope also includes the construction of two new access ramps between Patterson and Yale Streets that will provide improved access to/from Yale Street and Heights Boulevard.

Additional Work:

Schematic Drawings: See the Katy Freeway website at www.katyfreeway.org. Project will be updated on this site soon.

CLICK HERE FOR A PDF FILE MAP of the Proposed Revised Project

Construction Timeline: Contract letting in January 2010 with a 32-month construction duration.